Mar 5-9, 2001

This week's days worth of stone work occurred Thursday. The contractor was here, too, preparing the cabinet top for its stone covering. The wash basins are going to be attached directly to the stone with adhesive, so the wood support was removed from both the sink and faucet/controls location. I checked that the cabinet doors clear the counter top -- it makes it by about 1/4 inch: perfect.

shower area shower area detail counter top counter top door clearance tub platform drain tub platform drain (top) wash area wall