Bath remodel: Week 40

Last updated (UTC) $Date: 2007/06/07 03:08:36 $

May 14-18, 2001

The cladding arrived Monday. We want it to sit on site for a while before installing... the concern is stretch/shrinkage. Tuesday was a busy day with the contractor and stone fabricators here finishing up the stone work. The shelves in the shower, around the tub, in Mitsuko's washing area, and on the center vanity are done. They look great.

shower room shelves around the tub Mitsuko's washing area center vanity much of the wet area


The exhaust fan was installed. Instead of putting the fan in its standard box a box was made from sheet metal inside the space between toilet room ceiling and roof. This allows the fan to be installed below the peak of the roof and out of site. It's also relatively quiet.

Hidden fan back side of toilet room side view of fan external view