Bath remodel: Week 46

Last updated (UTC) $Date: 2007/06/07 03:08:37 $

June 25-29, 2001

On Monday the stone people polished the areas that needed polishing. They are now done (yeah!). The sealers still need to come in and seal the 6 stone shelves that were added a few weeks ago. The toilet room wall is also complete on the outside. We're ready for glass (to be installed Wednesday).

wall all the way to the floor window sill window sill close-up

I was away most of the week. It was quite nice to come home and find that the glass has been installed. There are still some gaskets needed around the shower/steam room door. They can do that when they come back to install the mirror.

sand-blasted kitty toilet window, door open toilet door closed shower enclosure shower door towel bars on partition